> San Francisco proposed a new bus lane on Van Ness in 2001. Its opening was delayed to 2022, yielding a project duration of around 7,600 days. “The project has been delayed due to an increase of wet weather since the project started,” said Paul Rose, a San Francisco Municipal Transportation Agency spokesperson. The project will cost $310 million, i.e. $100,000 per meter. The Alaska Highway, mentioned above, constructed across remote tundra, cost $793 per meter in 2019 dollars.

A similar example – the Golden Gate Bridge was built in 4 years in the 1930s at a (inflation adjusted) cost of $500M, ahead of schedule and 10% under budget. A project to install suicide nets below the bridge started in 2008 and is still ongoing after multiple delays, with a total projected cost of $211M.